The construction of a Next Generation Modular Home takes about a third of the time required to build a comparable conventional “stick-built” home. This time saving adds to YOUR bottom line!
We’ve outlined the steps translated into time for the construction of your Next Generation Modular Home. Review them in detail below and feel free to print our handy timeline sheet, that will show you a side-by-side comparison as well.
| Example of a 3,000 sq. ft house (barring any potential weather issues) |
| |
Modular Construction |
Timeframe |
| |
Site Preparation |
|
| |
Grading and site preparation |
Week 1 to 3 |
| |
Foundation |
|
| |
Curing of foundation |
|
| |
|
|
| |
Construction at Factory |
|
| |
Framing |
Week 4 to 5 |
| |
Installation of windows and Exterior doors |
|
| |
Roofing |
|
| |
Rough electrical |
|
| |
Rough plumbing |
|
| |
Rough HVAC |
|
| |
Insulation |
|
| |
Drywall |
|
| |
Underlayment |
|
| |
Interior doors installed |
|
| |
Window, door & base trim installed |
Week 6 |
| |
Painting |
|
| |
Bathroom and kitchen counter tops and cabinets |
|
| |
|
|
| |
Modular is delivered to your site - On-site finishes begin |
| |
Finish electrical |
Week 7 |
| |
Finish plumbing |
|
| |
Siding installed |
|
| |
Finish HVAC |
Week 8 to 11 |
| |
Hookup to water main, or well drilling |
|
| |
Hookup to sewer or installation of a septic system |
|
| |
Carpet and flooring |
Week 12 to 13 |
| |
Finish painting (Touch up) |
|
| |
Punch list & Move-in |
Week 14 |
| |
|
|
| |
Total |
14 Weeks (approx.) |